CompTIA Project Exam

Question No: 31

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release-FlRST?

  1. RFO

  2. RFI

  3. RFP

  4. RFQ

Answer: A

Question No: 32

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?

  1. Update the scope management plan.

  2. Modify the project baselines.

  3. Implement change control management.

  4. Inform the stakeholders of the issue.

Answer: D

Question No: 33

A new project sponsor has joined the project team, and the constraints on the project have

been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority Which of the following effects is this MOST likely to have on the project?

  1. The deliverables and quality will remain the same, but the cost will increase

  2. The deliverables and quality will remain the same, but the cost will decrease.

  3. The deliverables and cost will remain the same, but the quality will increase.

  4. The cost and quality will remain the same, but the deliverables will increase.

Answer: A

Question No: 34

A project manager is unsure if the quality of a deliverable from a SME meets specifications Which of the following is the BEST way for the project manager to address the issue?

  1. Conduct a face-to-face or telephone meeting with the team member.

  2. Send an email outlining the concerns to the team member.

  3. Schedule a project team meeting to obtain feedback from everyone.

  4. Post the issue on the wiki page for input from stakeholders

Answer: C

Question No: 35

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

  1. Project manager and project scheduler

  2. Project coordinator and project sponsor

  3. Project champion and project scheduler

  4. Project stakeholders and project team

Answer: A

Question No: 36

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?

  1. Project charter

  2. Project management plan

  3. Project statement of work

  4. Project schedule

Answer: B

Question No: 37

A project team is composed of numerous team members who are located throughout a country All personnel have identified core business hours A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

  1. Email

  2. Social media

  3. Text messaging

  4. Face-to-face

Answer: A

Question No: 38

Which of the following describes a burn rate?

  1. The rate at which project documents are disposed

  2. The rate at which project personnel leave the project

  3. The rate at which the project budget is used

  4. The rate at which the timeline increases

Answer: C

Question No: 39

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project take?

  1. Assess the risk register#39;s new items.

  2. Review the task start and finish dates.

  3. Obtain additional resources

  4. Analyze the assigned hours.

Answer: C

Question No: 40

In which of the fallowing organizational structures would a project manager have the MOST authority?

  1. Projectized

  2. Strong matrix

  3. Balanced matrix

  4. Functional

Answer: D

100% Ensurepass Free Download!
Download Free Demo:PK0-004 Demo PDF
100% Ensurepass Free Guaranteed!
Download 2018 EnsurePass PK0-004 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.